Aker BP Installs Valhall Flank West Topsides

Graphic for News Item: Aker BP Installs Valhall Flank West Topsides

The Valhall Flank West topsides were installed on the Aker BP-operated Valhall field located in the North Sea offshore Norway on Saturday, June 22, 2019. First oil from the project is expected in the fourth quarter 2019.

Aker BP said on Saturday that this was just 14 months after the first steel was cut at Kværner’s yard in Verdal. Both the topsides and the jacket were delivered ahead of schedule and under budget. The platform’s jacket was delivered by Kaverner in April this year.

Hot Tip

Looking for your next job? Register and build a detailed profile on Oil and Gas People so recruiters can find you. Apply for jobs with one click, store all of your employment documents in one place and receive job alerts as soon as suitable positions go live.

Aker BP is the operator of the Valhall Flank Vest with Pandion as a partner. The platform is the first to be delivered under the wellhead platform alliance between Aker BP, Aker Solutions, Kværner and ABB.

It sailed from Kværner in Verdal on Sunday, June 16 and arrived at the field with no carry-over-work from the yard. That means a significant reduction in the work scope offshore, Aker BP explained.

“This is probably the most complete platform ever installed in the North Sea. All planned construction work is complete and just seven percent of the commissioning phase remains. I am truly impressed by the job the alliance has done here,” said CEO Karl Johnny Hersvik in Aker BP.

Hot Tip

Register on Oil and Gas People as a candidate and always have full control of your visibility. We want recruiters to be able to instantly find candidates that are available and actively looking for work. Just confirm your status every 60 days to stay visible and at the top of recruiters searches.

“We see a definite effect from the alliance model in the Valhall Flank West project. Compared with similar projects, we have seen substantial reductions in both cost, engineering hours and construction of the topsides and jacket,” said Hersvik.

Installation

Heerema’s Thialf lifting vessel placed the 2000-tonne topsides on the jacket at Thursday evening. The entire operation was complete on Saturday morning.

The critical hook-up work starts almost immediately. Initially, crews will be transported to the platform using vessels. The Maersk Invincible jack-up rig is expected to arrive at the field sometime this week. It will drill six wells as part of the project and will function as a living quarters platform in the hook-up and commissioning phase.

“So far, Valhall Flank West has been a fantastic journey and I am proud to lead this team. All the alliances are delivering and the project is successful because we have a solid team that cooperates really well across companies,” says project manager Michael Joseph Bible.

Hot Tip

Oil and Gas People gives recruiters a live snapshot of the current oil and gas workforce and its availability. Update your profile every 60 days to stay visible to recruiters as actively looking. Better for candidates.. Better for recruiters..

At the Valhall Field Center, the Modification alliance has carried out extensive modifications over the past year to prepare the center to receive the production from Valhall Flank West. In addition, the Subsea alliance has laid pipelines and umbilical which are ready to be pulled in now that the platform is in place.

“We are now entering a demanding offshore period, and we will continue the good work in this phase of the project. The most important thing for us is that everyone working in the project return home safely,” says Bible.

First oil in 4Q 2019

Valhall has produced one billion barrels since the field opened in 1982. The ambition is to produce another billion barrels during the next 40 years, Aker BP said.

“Valhall Flank West is an important contribution to ensure that we achieve our ambition. The field can contribute around 60 million barrels of oil equivalents to Valhall’s production. The West Flank has capacity for another six wells, and we are now looking into the possibility of more wells and increased value creation from the field,” said Valhall asset manager Per Mikal Hauge.

Hot Tip

Other job sites dump your CV into a database and let recruiters shift through thousands of candidates to find out who is available. With Oil and Gas People you just update your profile every 60 days to stay visible and at the top of recruiter searches.

Aker BP is investing NOK 5.5 billion in Valhall Flank West. The break-even price for the development is $28.5 per bbl. Around 1500 people have been involved in the project.

“There is high activity on the Valhall field. Last week, we removed QP from the field centre, the first of three old platforms that will be taken away. We are also investing in the future of the field with new wells and plugging of shut down wells. We look forward to starting production from Valhall Flank West in the fourth quarter. What has been installed on the field is of very good quality, and that project has set a new standard for project implementation. Today, I would just like to congratulate everyone who has been involved in the field development so far,” Hauge concluded.